Today is blowing snow and getting colder but the lower level is getting closed in. Outer wall board is being installed. They also unloaded steel studs to the fourth floor as well.
They are moving up at a rate of one floor a week. About the same rate as the Drake but twice the footprint. These guys are working at a quick pace . Some shots from yesterday and today.
Last edited by Design-mind; Nov 25, 2012 at 2:45 AM.
Lots going on. Construction lift going up on south side of building and moving of forms to start the 12th floor. Pictures I took today. It pays to have friends in high places, literally. LOL!
Updates from today. The workers usually see me taking pictures and wave. Today they posed, so I tip my hat to their work by posting them in fine form. Work has started on floor 12!
Forgot to mention that the 12 floor is getting really close to the crane so they will probably jump the crane one section tomorrow. I will try to get some pictures.