http://ottawa.ca/calendar/ottawa/cit...sition6eng.htm
2. OTTAWA ROAD 174 ENVIRONMENTAL ASSESSMENT
CUMBERLAND (19)

WHEREAS Ottawa Road 174 is a fundamental transportation link and critical to future growth in Orléans and continuing east; and

WHEREAS to accommodate growth west of Trim Road along OR 174, the City of Ottawa will be completing an Environmental Assessment on the widening of OR 174 from the Highway 417/174 split to Jeanne D’Arc, as identified as a Phase 1 and Phase 2 project in the Transportation Master plan; and

WHEREAS the planned Ministry of Transportation widening of Highway 417 from Nicholas Street to the 417/174 split is anticipated to be completed prior to 2016; and

WHEREAS the City of Ottawa’s Official Plan and Transportation Master Plan does not currently identify the need to widen OR 174 east of Jeanne D’Arc; and

WHEREAS in 2008 the Province of Ontario offered the City of Ottawa $5M to fund an Environmental Assessment for the widening of OR 174 / Prescott Russell Road 17; and

WHEREAS the Provincial offer of $5M is still available;

THEREFORE BE IT RESOLVED that the Provincial offer of $5M to complete an Environmental Assessment of the widening of OR 174/Prescott Russell Road 17 be utilized under the following conditions:

a) That the widening of Highway 417 to fix the split westerly to Nicholas Street is fully funded with a commitment to implement by 2015;
b) All costs related to the City of Ottawa’s planned Environmental Assessment from 417/174 split easterly to Jeanne D’Arc be drawn from the Provincial offer of $5M;
c) The remaining funds be used to complete the Environmental Assessment of OR 174 / Prescott-Russell Road 17 from Jeanne D’Arc easterly and that the study be borne by the Province or the United Counties of Prescott and Russell with the City providing input on the scope of the study prior to the call for proposals;
d) That the Environmental Assessment from Jeanne D’Arc easterly look at the downstream effect on the City’s infrastructure, and that the study include a cost benefit analysis and a full exploration of all alternatives; and,
e) That the Environmental Assessment from Jeanne D’Arc easterly requires final approval by City of Ottawa Council.

BE IT FURTHER RESOLVED that the results of the Environmental Study for the widening of OR 174 from Jeanne D’Arc easterly be considered and incorporated into the City’s updated Transportation Master Plan.

CARRIED
Reply With Quote
     
     
End
 
 
 

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 2:16 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.