  #61  
Old Posted Jul 28, 2022, 3:55 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
Have made some progress on forming and pouring L1 walls and posts on the west end of pit. Slowly progressing towards the east end.
Reply With Quote
     
     
  #62  
Old Posted Sep 3, 2022, 3:07 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
Have now got forming and steel rebar in for the far west end of pit for the ground floor slab. Could see a concrete pour in the next few weeks.
Reply With Quote
     
     
  #63  
Old Posted Oct 14, 2022, 9:01 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
Slowly making progress on the L1 level walls and posts towards the east side of pit. Doesn't appear that they have poured any of the ground floor slab yet on the west side.
Reply With Quote
     
     
  #64  
Old Posted Nov 12, 2022, 4:11 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
Looks like they have finally poured some of the ground floor slab on the west end of pit and have forming up for the first ground floor walls there. Still working on the L1 footings and posts and walls on the east side of pit thou.
Reply With Quote
     
     
  #65  
Old Posted Nov 27, 2022, 2:35 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
First ground floor walls are now poured on the west end and have now poured another section of the ground floor slab in the SW corner. Still working on the footings and L1 posts and walls on the east side of pit.

Last edited by jammer139; Nov 28, 2022 at 2:37 PM.
Reply With Quote
     
     
  #66  
Old Posted Dec 16, 2022, 8:04 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
They were completing the ground floor slab pour today along the south side of the pit. Still have alot of forming to do along the northeast side of the pit to complete the underground level.
Reply With Quote
     
     
  #67  
Old Posted Jan 12, 2023, 8:57 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
Still forming the ground floor slab in the NE of pit. Have likely poured the L1 floor slab now for entire footprint.
Reply With Quote
     
     
  #68  
Old Posted Apr 12, 2023, 2:49 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
Ground floor slab is now completed. Have around 40% of the ground floor walls and posts poured on the west end of this project. Given its Drewlo will likely take another 6 weeks to complete the ground floor walls and posts.
Reply With Quote
     
     
  #69  
Old Posted Apr 12, 2023, 3:46 PM
MolsonExport's Avatar
MolsonExport MolsonExport is online now
The Vomit Bag.
 
Join Date: Oct 2003
Location: Otisburgh
Posts: 44,921
I reckon that the Great Pyramid of Khufu was built faster than some Drewlo buildings.
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell)
Reply With Quote
     
     
  #70  
Old Posted Apr 26, 2023, 11:29 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
Have maybe 60% of the ground floor walls and posts poured now and have started forming for 2nd floor slab on the west end. Have not even got forming up yet for ground walls and posts on the east end at this point.
Reply With Quote
     
     
  #71  
Old Posted May 14, 2023, 8:43 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
Forming for the 2nd floor slab is started on the west end. Forming for the final ground floor walls and posts is started on the east end.
Reply With Quote
     
     
  #72  
Old Posted May 16, 2023, 2:35 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
Drewlo has updated their website for this building. Will actually be 11s.


https://www.drewloholdings.com/comin...riage-place-ii
Reply With Quote
     
     
  #73  
Old Posted May 31, 2023, 1:06 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
They have finally finished the ground floor wall and post pours and have started pouring some of the 2nd floor walls and posts on the west end.
Reply With Quote
     
     
  #74  
Old Posted Jun 29, 2023, 8:07 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
They have poured some of the 3rd floor walls and posts on the west end now. The rest of the 2nd floor walls and posts are now poured. Forming for 3rd floor slab continues in the center section.
Reply With Quote
     
     
  #75  
Old Posted Jul 22, 2023, 7:20 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
Looks like work has stalled again with no visible progress since June.
Reply With Quote
     
     
  #76  
Old Posted Jul 28, 2023, 1:27 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
Don't understand why Drewlo has halted construction on this building. Is it a lack of workers, financial, engineering code issues?
Reply With Quote
     
     
  #77  
Old Posted Aug 23, 2023, 2:23 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
Drewlo has crews back working on site now on the 3rd floor slab and walls.
Reply With Quote
     
     
  #78  
Old Posted Sep 14, 2023, 7:48 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
Looks like they may have finally finished forming and pouring the 3rd floor walls in the NE corner. The 4th floor slab may has also finally been poured on the west end as they have now started putting up 4th floor wall forms. I suspect Drewlo is directing the lions share of their concrete forming crew to the 16s Talbot St building in an effort to get it topped out before the end of the year. Hopefully once that happens the concrete forming crew can focus on this 11s building thru next winter and spring.
Reply With Quote
     
     
  #79  
Old Posted Oct 10, 2023, 11:52 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
They have finished pouring the 4th floor slab on the west end and are forming and pouring some of the west end 4th floor walls. The east end is now wrapping up the 4th floor slab and starting forming for the 4th floor walls.
Reply With Quote
     
     
  #80  
Old Posted Oct 26, 2023, 1:38 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,795
They have finished pouring all the 4th floor walls and posts now and have poured some of the west end 5th floor slab as they have 5th floor wall forming started on that end. Still have the eastern half of the 5th floor slab to form. They should get a boost of manpower in a couple of weeks when the concrete forming crew on Talbot St finishes their work there.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 4:08 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.