Truckload of steel rebar being delivered this morning and small crew forming a footing for what should be the tower crane base. Could see it poured by the end of next week. Might see mobile crane on site by end of Sept to setup tower crane.
Tower crane is now assembled. Mobile crane being packed up to be taken away. Strange they seem to have left the pieces of a tower crane on the field to the east of the site. They must have brought in other tower crane pieces to complete the assembly.
Today they were trucking away the pieces of the tower crane they had parked in the empty lawn east of the site. For some reason they ended up assembling a different tower crane for the build.
Excavating for the sump pump pit footings now started in the SE corner of the pit. Most of the L2 walls and posts are now poured in the remaining corners of the pit.
Still working on forming L2 walls and posts for the foundation. Should be getting close to pouring the L2 floor slab in part in the next weeks depending on the weather.