Work activities completed thru August 1, 2008:
• Level 10 east side deck concrete pour completed on July 29, 2008
• Level 10 deck 100% complete
• Level 11 deck 90% complete of all structural reinforcement, embeds and MEP rough-in
• Level 11 concrete deck to pour on August 2, 2008
• Level 12 vertical structural members to start on August 5, 2008
• Level 12 deck pour scheduled for August 12, 2008
• CMU walls complete in podium to Level 8
• Structural stairs complete in podium to Level 8 at the 3 locations
• Electrical primary feed rough-in begins
• Mechanical and plumbing rough-in continues at all levels including the first condo floor at Level 11
• Ownership hosts an “invitation only” public relations event for the media on July 31, 2008
• Media escorted to Level 10 for viewing and filming of pool deck and for project overview presentation and
comments