I'm glad they're doing this, but is there no where closer to MAX that could have been zoned this way? I mean, here we have a linear area of land that is 1) far away from the MAX line and 2) runs perpendicular to it anyway. As much as like seeing higher density requirements in the suburbs, this doesn't do much for me.
Reply With Quote
     
     
  #282  
Old Posted Apr 8, 2012, 5:27 PM
philopdx philopdx is offline
Registered User
 
Join Date: Feb 2008
Location: Deep South
Posts: 1,275
Update from 4-7-2012:

Reply With Quote
     
     
  #283  
Old Posted May 18, 2012, 3:05 AM
MarkDaMan's Avatar
MarkDaMan MarkDaMan is offline
Moderator
 
Join Date: May 2005
Location: Portland
Posts: 7,513
Beaverton and ScanlanKemperBard Companies complete $22 million combined purchase at the Round
Published: Thursday, May 17, 2012, 2:53 PM Updated: Thursday, May 17, 2012, 4:57 PM
By Dominique Fong, The Oregonian

http://www.oregonlive.com/beaverton/...kemperbar.html

Quote:
The $22 million sale of four buildings at the Round at Beaverton Central has been completed, laying the foundation for an anticipated rebirth of the city's downtown core.

In early April, the city of Beaverton bought the South Office building, commonly known as the Coldwell Banker building, for $8.65 million and approved spending an extra $200,000 for closing costs.

Portland-based ScanlanKemperBard Companies, a real estate equity firm, bought three remaining buildings for $13.25 million in a deal that closed April 27, according to global real estate firm Jones Lang LaSalle, which managed the two transactions...
Quote:
...The public's stake in the Round may grow larger, as officials consider moving City Hall to the Coldwell Banker Building. Feasibility studies evaluated the potential for administrative offices, a municipal court and police department, but officials said nothing has been confirmed...
Quote:
...The city will design and install ground-level parking lots until the market improves, said Don Mazziotti, the city's director of community and economic development.

In the meantime, the city is working with engineering consultant Cardno WRG in Portland to improve the south plaza, Mazziotti said. His department will also support small businesses that have offices on the third floor of the Coldwell Banker building...
__________________
make paradise, tear up a parking lot
Reply With Quote
     
     
  #284  
Old Posted May 22, 2012, 3:29 PM
MarkDaMan's Avatar
MarkDaMan MarkDaMan is offline
Moderator
 
Join Date: May 2005
Location: Portland
Posts: 7,513
Hillsboro planning massive AmberGlen development
POSTED: Monday, May 21, 2012 at 03:16 PM PT
Daily Journal of Commerce BY: Reed Jackson

http://djcoregon.com/news/2012/05/21...n-development/

Quote:
Hillsboro’s suburban skyline could soon become taller.

The city recently approved an ordinance to rezone a Tanasbourne business park and make way for the AmberGlen Community Plan, a 20-year growth strategy expected to produce multiple commercial and residential high-rise buildings.

The 606-acre development planned between 185th and 206th avenues will create more shopping and dining opportunities, but also provide convenient housing options for people working at technology and retail corporations nearby, said Colin Cooper, a planning manager for the city. It also will help Hillsboro handle the influx of residents but remain inside the urban growth boundary...
Quote:
...Approximately 6,000 new medium- to high-density residential units are expected to be built, as well as 3 million square feet of office space and 500,000 square feet of retail. A large park will sit in the middle, while green pathways will be spread throughout to connect the property to Rock and Bronson creeks.

Transportation access will also be a key element of the development; a facility is being planned to incorporate multiple TriMet bus lines and the MAX blue line...
Quote:
...However, at least one high-rise – residential or office – is expected to be built within the next five years, Cooper said.
__________________
make paradise, tear up a parking lot
Reply With Quote
     
     
  #285  
Old Posted Jun 12, 2012, 11:31 PM
MarkDaMan's Avatar
MarkDaMan MarkDaMan is offline
Moderator
 
Join Date: May 2005
Location: Portland
Posts: 7,513
Revived project will bring two new hotels to Hillsboro
Published: Tuesday, June 12, 2012, 4:21 PM
By Sally Ho, The Oregonian

http://www.oregonlive.com/hillsboro/...bring_two.html

Quote:
HILLSBORO -- The city has limited involvement with the two new hotels coming to Hillsboro, but the developer is no stranger to the scene.

Seattle-based developer, InnVentures, Inc., confirmed they hope to break ground as early as this month on a 4.9-acre plot at Northwest Tanasbourne Drive and Northwest John Olsen Place. The company already operates three other hotels in the city (and one each in Tigard and Portland), including two Marriott properties about a half mile from the site of the new hotels.

The first of the new hotels will be a seven-story, 165-room Embassy Suites and will be built on the northwest corner, according to the land use approval documents. A second hotel will sit adjacent on the northeast side of the land as a four-story, 106-room Hampton Inn and Suites...
Quote:
...The Hampton Inn will be a smaller hotel with a lower price point. The Embassy Suites will be a full-service, long-stay hotel, with a restaurant and meeting rooms. At seven stories, the Embassy Suites will also become the city’s building with the most floors, although it won’t be the tallest. That title will remain with Intel's D1X plant, Cooper said...
__________________
make paradise, tear up a parking lot
Reply With Quote
     
     
  #286  
Old Posted Jun 13, 2012, 1:38 AM
philopdx philopdx is offline
Registered User
 
Join Date: Feb 2008
Location: Deep South
Posts: 1,275
I work RIGHT THERE. I guess it's going to be on the lot adjacent to the already developed lots at the intersection of the two roads.

Exciting stuff. Keeping track of this will be a breeze for me.
Reply With Quote
     
     
  #287  
Old Posted Jun 21, 2012, 9:09 PM
zilfondel zilfondel is offline
Submarine de Nucléar
 
Join Date: Mar 2006
Location: Missouri
Posts: 4,477
Yakima Bears agree to Hillsboro's terms for baseball deal

Quote:
“The team and the (Northwest) League have approved the term sheet and all aspects of this project are moving forward,” Willey said at about noon in Tuesday’s online chat. “We don't foresee any issues to progressing to our ultimate goal of playing baseball in June 2013.”

The 20-year offer sheet was approved unanimously by the city on June 5 and the team and league approved it -- without changes -- on June 8, according to city spokeswoman Mary Loftin.

pic from Oregonlive.com, city of Hillsboro

http://www.oregonlive.com/hillsboro/...tml#incart_mce
Reply With Quote
     
     
  #288  
Old Posted Jun 21, 2012, 9:12 PM
zilfondel zilfondel is offline
Submarine de Nucléar
 
Join Date: Mar 2006
Location: Missouri
Posts: 4,477
Quote:
Originally Posted by bvpcvm View Post
I'm glad they're doing this, but is there no where closer to MAX that could have been zoned this way? I mean, here we have a linear area of land that is 1) far away from the MAX line and 2) runs perpendicular to it anyway. As much as like seeing higher density requirements in the suburbs, this doesn't do much for me.
Should we have a looped MAX line to connect Hillsboro to Tigard? Or high-frequency bus service (remember the old "frequent bus" that Trimet touted 8 years ago?)?
Reply With Quote
     
     
  #289  
Old Posted Jul 1, 2012, 7:01 AM
philopdx philopdx is offline
Registered User
 
Join Date: Feb 2008
Location: Deep South
Posts: 1,275
New Orenco Apartments 6-29-2012:





Reply With Quote
     
     
  #290  
Old Posted Jul 1, 2012, 7:09 AM
philopdx philopdx is offline
Registered User
 
Join Date: Feb 2008
Location: Deep South
Posts: 1,275
D1X 6-29-2012: Linked to larger image

Reply With Quote
     
     
  #291  
Old Posted Jul 13, 2012, 2:59 AM
MarkDaMan's Avatar
MarkDaMan MarkDaMan is offline
Moderator
 
Join Date: May 2005
Location: Portland
Posts: 7,513

Courtesy: City of Hillsboro

Hillsboro Baseball: Evolution of a deal

Published: Thursday, July 12, 2012, 5:24 PM Updated: Thursday, July 12, 2012, 6:12 PM
By Sally Ho, The Oregonian

http://www.oregonlive.com/hillsboro/..._river_default

Quote:
The Oregonian obtained drafts of the negotiated term sheet between the city of Hillsboro and Short Season LLC. Here is a detailed summary and analysis (in italics) of the five drafts that defined the deal for the Yakima Bears' relocation to Hillsboro next season:


Draft 1, April 6, 2012:

STADIUM COSTS: Team to contribute unspecified amount of money to the stadium build - This clause is eliminated in all subsequent drafts

RENT: $150,000 with 3 percent annual increase - It remains throughout negotiations, despite the team hitting back in an email after Draft 4

PRE-DEVELOPMENT COSTS: Team to pay all pre-approved, pre-development expenses, including consulting and legal fees - An unspecified maximum amount for this clause appears in Draft 2 but the clause is eliminated entirely in subsequent drafts

PARKING: City to keep all parking revenue - This clause is amended in drafts 2, 4 and 5, but the city eventually prevails with full control of operations and revenue

TICKETS: Team to pay a $2 per-ticket surcharge to the city - This clause is amended in drafts 3, 4 and 5, moving the city from collecting up to $3, down to just the prevailing $1

PROFIT-SHARING: After the first $250,000 in net revenue, 50-50 profit sharing for game events and 70-30 profit sharing for the city and team, respectively, for non-game team events - Profit sharing for non-game team events is eliminated in Draft 3 and the entire clause disappears in Draft 4 and 5

REPAIRS: Team to pay for 25 percent for capital repairs and maintenance beyond $200,000 - This is changed to $250,000 in Draft 2

POURING RIGHTS: Revenue from the third-party beverage distributor to be split 80-20 between city and team, respectively; Sale of alcohol is an open issue - Non-alcoholic beverages is added in Draft 2 and no mention of alcohol appears again

CONCESSIONS: If the city controls concessions by hiring a third-party operator, the operator will pay the team the net revenue from team events; If the team controls concessions, the team must pay 20 percent of the net revenue to the city – Term is amended in every draft and the city and team agree in Draft 5 to create a separate agreement for concessions


Draft 2, April 19, 2012

PARKING: Amended for city to keep either $2 per vehicle or 50 percent of all revenue (whichever is greater) for team events; Team and city to decide who will operate parking


Draft 3, April 20, 2012

RENT: Amended to a 20 percent rate increase on the 6th, 11th and 16th anniversaries - The increase is changed back to the 3 percent annual in drafts 4 and 5

TICKETS: Amended to a defined $2 surcharge, with $1 to the city and $1 to a capital expenditure fund -- controlled by the city -- for repairs; The fund will cover the team’s portion of repairs beyond $250,000; Beyond the first 100,000 tickets in a season, another $1 surcharge will be allocated to the city - The third dollar surcharge is eliminated in Draft 4; In Draft 5, the surcharge is lowered to $1 and the city-controlled fund is eliminated


Draft 4, May 7, 2012
PARKING: The clause is changed to $3 per vehicle or 50 percent of all revenue (whichever is greater) for team events; the city is to operate parking

In response to this draft, Northwest League President Bob Richmond writes in an email: “...the league members were very clear they will not approve the current revenue lines with the proposed rent increases, parking lot split and ticket surcharge.” Richmond asks if the city will consider taking a percentage of the ticket price, instead of a flat dollar amount. He also insists the team control concessions at the stadium at all times.


Draft 5, June 5, 2012 - This term sheet is approved and is the framework for the official contract. See it here.

RENT: $150,000 with 3 percent annual increase


CONCESSIONS: Team to run concessions at the stadium for the first two years, keeping all profits during game days; City and team will approve a separate agreement for concessions

PARKING: City to keep all parking revenue and operate parking

TICKETS: Team to pay a $1 ticket surcharge

Although terms were introduced, the prevailing term sheet has the team free from a financial contribution to the stadium, the pre-development costs and any profit-sharing with the city.

Full terms of the concessions and naming rights remain unseen, because the approved term sheet calls for a separately negotiated agreement for those terms. The pouring rights clause disappears but could reappear as part of the separate concessions agreement.
Quote:
By The Numbers

Hillsboro stadium cost: Between $13.4 million and $15.2 million

Vancouver stadium cost: Up to $23 million

Short Season's financial contribution for Vancouver: Up to $6.9 million

Short Season's financial contribution for Hillsboro: $0

Number of negotiation drafts required: 5

Number of days from first to last negotiation draft: 60 days

Negotiated rent: $150,000 with 3 percent annual increase

Rent revenue at the end of the 20-year contract: $4,030,556.07
Annual cost to city taxpayers for bond: About $1 million
__________________
make paradise, tear up a parking lot
Reply With Quote
     
     
  #292  
Old Posted Jul 25, 2012, 1:30 AM
edirp edirp is offline
Registered User
 
Join Date: Apr 2004
Posts: 669
"Living Green" Apartments

These apartments are looking even more uglier as construction continues. A hodgepodge of too many paint colors, brick colors, and wood siding styles. Yuck.

Quote:
Originally Posted by philopdx View Post
New Orenco Apartments 6-29-2012:






Last edited by edirp; Jul 25, 2012 at 3:18 AM.
Reply With Quote
     
     
  #293  
Old Posted Jul 25, 2012, 4:06 AM
2oh1's Avatar
2oh1 2oh1 is offline
9-7-2oh1-!
 
Join Date: May 2007
Location: downtown Portland
Posts: 2,478
Wow, they really nailed the outlet mall look, didn't they?
Reply With Quote
     
     
  #294  
Old Posted Jul 28, 2012, 12:10 PM
RED_PDXer RED_PDXer is offline
Registered User
 
Join Date: Dec 2007
Location: Portland, OR
Posts: 794
Quote:
Originally Posted by zilfondel View Post
Yakima Bears agree to Hillsboro's terms for baseball deal




pic from Oregonlive.com, city of Hillsboro

http://www.oregonlive.com/hillsboro/...tml#incart_mce
I hope Milwaukie gets a team too. I'm not driving out to Hillsboro.
Reply With Quote
     
     
  #295  
Old Posted Sep 18, 2012, 10:34 PM
Nunya Nunya is offline
Registered User
 
Join Date: Dec 2011
Posts: 83
Mill Creek Apartments

http://www.bizjournals.com/portland/...n-stalled.html

Quote:
A luxury apartment project slated for the Bridgeport area is back on track after being shelved during the recession.

Mill Creek Residential Trust LLC has begun site work on Bridgeport Apartments, a $70 million mixed-use project that straddles the Tualatin-Durham line and promises to bring city-style apartments to the suburbs. Formal ground breaking ceremonies will be held at 11 a.m. Sept. 25 at the site, 18045 S.W. Boones Ferry Road.
Reply With Quote
     
     
  #296  
Old Posted Sep 18, 2012, 10:39 PM
Derek Derek is online now
Registered User
 
Join Date: Aug 2006
Location: Portland, OR
Posts: 9,540
Whoa. 800 parking spaces for 367 units. At least the article states they're supposed to be hidden, but damn.
__________________
Portlandia
Reply With Quote
     
     
  #297  
Old Posted Sep 19, 2012, 2:10 AM
MarkDaMan's Avatar
MarkDaMan MarkDaMan is offline
Moderator
 
Join Date: May 2005
Location: Portland
Posts: 7,513
From leebarc.com, not sure if this is still the current design....


http://www.leebarc.com/#/mixed_use/alexan_bridgeport/1/
more rendings at the above link^
__________________
make paradise, tear up a parking lot
Reply With Quote
     
     
  #298  
Old Posted Sep 19, 2012, 2:52 AM
maccoinnich maccoinnich is offline
Moderator
 
Join Date: Jan 2009
Location: Portland
Posts: 7,389
"bring city-style apartments to the suburbs". Ahem.
__________________
"Maybe to an architect, they might look suspicious, but to me, they just look like rocks"

www.twitter.com/maccoinnich
Reply With Quote
     
     
  #299  
Old Posted Sep 19, 2012, 3:01 AM
tworivers's Avatar
tworivers tworivers is offline
Registered User
 
Join Date: Feb 2006
Location: Portland/Cascadia
Posts: 2,598
yuck.
Reply With Quote
     
     
  #300  
Old Posted Sep 19, 2012, 3:22 AM
bvpcvm bvpcvm is offline
Registered User
 
Join Date: Apr 2004
Location: Portland
Posts: 2,788
wow, cool!

</sarcasm>
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > United States > Pacific West > Portland > Portland Suburbs and the State of Oregon
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 9:14 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.