  #41  
Old Posted Jan 15, 2024, 9:01 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,865
Wrapping up the 5th floor concrete block walls on the 5s rental building and should see the precast roof slabs being installed over the next two weeks.
Reply With Quote
     
     
  #42  
Old Posted Jan 23, 2024, 7:03 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,865
Have now landed the roof pre-cast slabs on the south wing of the 5s rental building. Also excavator and dump trucks working to clear the small hill of soil where the 2nd 5s building is planned. We could see the foundation for the second 5s building being dug out this spring.
Reply With Quote
     
     
  #43  
Old Posted Feb 4, 2024, 5:25 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,865
The second tower crane has now been removed further reducing the number of tower cranes standing in the city. The 5s rental building has now completed the 5th floor roof slab installation. And the hill of dirt to the east has now been cleared where the second 5s building is to get built.
Reply With Quote
     
     
  #44  
Old Posted Feb 27, 2024, 8:33 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,865
Have now got window units installed up to the 5th floor in both the retirement building and apartment building. Insulation board now being installed on the apartment building so could soon see the masonry contractor starting soon with the exterior brick veneer. The east side of the property is being cleared and levelled which could soon mean the start of the foundation for the second 5s apartment building.
Reply With Quote
     
     
  #45  
Old Posted Apr 27, 2024, 8:16 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,865
Exterior insulation on the 5s rental building is mostly done now and the masonry contractor is making good progress installing the exterior brick on the west side. The 6s retirement building is still getting the exterior wall insulation installed and most of the interior partition walls are now done with progress on the electrical, plumbing and HVAC rough in's. The second 5s apartment building to the east now has the site grading completed. Next step would be excavating for the foundation footings for this building.

Last edited by jammer139; Apr 28, 2024 at 5:11 PM.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 9:14 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.