Construction Schedule
January 2008 - Issuance of revised Master Use Permit by the City of Seattle
April 2008 - Demolition of administrative building will commence
June 2008 - Completion of demolition
August 2008 - Repair of Sanctuary building
October 2013 - Shoring & Excavation will commence
September 2014 - Construction of High Rise portion of project will commence
January 2015 - Rehabilitation of the Sanctuary building will commence
July 2016 - Completion of the building and tenant move-in
October 2016 - Opening of the hotel