A report I just read indicated that a massive oversight in the positioning and time line of the WTC 1's sub level loading docks are blocked by the temporary path station and will therefore impede the ability for tenants to move in by the completion date. As a result, for an extra cost of more than 50 million, temporary loading docks will have to be erected until the new path station is completed, and the old temporary one is removed.
Thanks alan for the update, 9 trucks!! how many lengths of steel are on a truck?! is it all for WTC 1?
Looking at Earthcam this morning I see four large bundles of steel at the base of the tower. One is quite large, possibly perimeter steel. Not sure how to post screenshots from an iPhone yet... Go to Earthcam and check out the tower 1 base cam.
9 trucks of steel due on site by 5am to avoid embargo due to parade, if winds are low, they will start bringing the steel up to deck at 7am and then start shaking it out.
Alan
Right on the money! Thanks for joining Alan! Your inside info is much appreciated!
__________________ I Love NY
September 11, 2001 Never Forget
Save water, shower with a friend!
SSP member since 2003
Please do not use any of my photos or videos without my permission. thanks
Everyone! 1WTC does have something to represent the NY Giants!
1WTC is a Giant! AND The Blue Netting at the top of the Tower represents the color of the NY GIANTS! OH YES! WE ARE BACK!
__________________ I Love NY
September 11, 2001 Never Forget
Save water, shower with a friend!
SSP member since 2003
Please do not use any of my photos or videos without my permission. thanks
__________________ I Love NY
September 11, 2001 Never Forget
Save water, shower with a friend!
SSP member since 2003
Please do not use any of my photos or videos without my permission. thanks
__________________ I Love NY
September 11, 2001 Never Forget
Save water, shower with a friend!
SSP member since 2003
Please do not use any of my photos or videos without my permission. thanks