  #321  
Old Posted Dec 7, 2017, 4:52 PM
KWillChicago's Avatar
KWillChicago KWillChicago is online now
Registered User
 
Join Date: Mar 2015
Location: Chicago
Posts: 89
So many support beams. I am so confused. Does anyone have a bluprint/diagram of what the the lower levels are going to look like?
Reply With Quote
     
     
  #322  
Old Posted Dec 7, 2017, 5:20 PM
donnie donnie is offline
Registered User
 
Join Date: Feb 2011
Posts: 99
I would imagine those are temporary!

On a side note what's the hold up on OCS? I take it the alderman didn't get a big enough cut wich is why he's the only one holding this project from entering the construction phase...
Reply With Quote
     
     
  #323  
Old Posted Dec 7, 2017, 8:14 PM
BVictor1's Avatar
BVictor1 BVictor1 is online now
Registered User
 
Join Date: Sep 2002
Location: Chicago
Posts: 8,918
Quote:
Originally Posted by donnie View Post
I would imagine those are temporary!

On a side note what's the hold up on OCS? I take it the alderman didn't get a big enough cut wich is why he's the only one holding this project from entering the construction phase...
It can't enter construction phase before approval phase. What's happening now is a formality to study traffic and obtain more feedback.

Relax!
__________________
titanic1
Reply With Quote
     
     
  #324  
Old Posted Dec 7, 2017, 9:19 PM
Fvn Fvn is offline
Registered User
 
Join Date: Nov 2017
Posts: 9
Quote:
Originally Posted by KWillChicago View Post
So many support beams. I am so confused. Does anyone have a bluprint/diagram of what the the lower levels are going to look like?
I think what they do is build up the parking level to below the beams and then take the beams out and build the next floor. the bracing is all temporary due to how the underground portion holds its self from falling in due to the floors taking up that stress

if you go back to january 2017 on the transbay block 5 webcam in San Francisco you can see more or less how its done (very similar bracing situation on that project)

https://app.oxblue.com/open/clarkconstruction/block5
Reply With Quote
     
     
  #325  
Old Posted Dec 8, 2017, 7:03 AM
donnie donnie is offline
Registered User
 
Join Date: Feb 2011
Posts: 99
Quote:
Originally Posted by BVictor1 View Post
It can't enter construction phase before approval phase. What's happening now is a formality to study traffic and obtain more feedback.

Relax!
What part exactly did you not understand?

Reply With Quote
     
     
  #326  
Old Posted Dec 8, 2017, 11:28 AM
harryc's Avatar
harryc harryc is online now
Registered User
 
Join Date: Jun 2007
Location: Oak Park, Il
Posts: 8,634
Dec 6







The gravel fill from the hole - protects the rebar that is sticking up out of the piling. The top of the rebar will be at or near the top of the foundation mat.


The pink loops are the rebar sticking out of the piling.


__________________
Harry C --- Chicago rep for SkyRise Cities ---- My Flickr stream HRC_OakPark
The man who trades freedom for security does not deserve nor will he ever receive either. B Franklin.
Reply With Quote
     
     
  #327  
Old Posted Dec 12, 2017, 1:29 AM
vexxed82's Avatar
vexxed82 vexxed82 is offline
Registered User
 
Join Date: Jun 2007
Location: Chicago
Posts: 211
Snapped a few shots on Sunday. My first visit to the project actually. Impressively large hole. Need to get back one day when they're working to add human scale. Definitely want to be around for the mat pour. Forum meet-up??







__________________
Nick Ulivieri | instagram | twitter | Facebook
Reply With Quote
     
     
  #328  
Old Posted Dec 12, 2017, 2:51 PM
KWillChicago's Avatar
KWillChicago KWillChicago is online now
Registered User
 
Join Date: Mar 2015
Location: Chicago
Posts: 89
I'm in nick. Just give me a date and time. Im still in the burbs but if i drive down that would give me a chance to walk over and see vista again as well.
Reply With Quote
     
     
  #329  
Old Posted Dec 12, 2017, 3:10 PM
harryc's Avatar
harryc harryc is online now
Registered User
 
Join Date: Jun 2007
Location: Oak Park, Il
Posts: 8,634
Quote:
Originally Posted by KWillChicago View Post
I'm in nick. Just give me a date and time. Im still in the burbs but if i drive down that would give me a chance to walk over and see vista again as well.
Wolf Point - 325 Hubbard - Reanelle - Apple - 465 Park - Vista, nice little stroll.
__________________
Harry C --- Chicago rep for SkyRise Cities ---- My Flickr stream HRC_OakPark
The man who trades freedom for security does not deserve nor will he ever receive either. B Franklin.
Reply With Quote
     
     
  #330  
Old Posted Dec 13, 2017, 6:44 PM
maru2501's Avatar
maru2501 maru2501 is offline
Registered User
 
Join Date: Oct 2015
Location: chicago
Posts: 821
Renelle kind of going up overnight at this point. Amazing how quick when you don't have to do a foundation of any kind
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Global Projects & Construction > Skyscraper & Highrise Construction
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 2:33 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2017, vBulletin Solutions, Inc.