School board HQ on target for summer opening
(Hamilton Mountain News, Gord Bowes, Dec 9 2013)

The windows will be going in soon and the interior of the building will start to take shape over the next few months, says the project manager of the public school board’s new Mountain headquarters.

“As long as it is enclosed in January I feel comfortable it is progressing (on schedule),” said Melissa Cohen-White, and the project should be be ready for staff to move in during July.

The building should be closed in by the end of January, she said. Some interior work which doesn’t depend on the building being enclosed has already begun, she said.

Exterior work such as the aluminum cladding will be done after that, but all the interior work such as drywalling can proceed, said Cohen-White.

Central Mountain councillor Scott Duvall said traffic lights will be installed at the intersection of Upper Wentworth and Fieldway Drive, which is being renamed Education Court, to help with increased traffic in and out of the area.

The tender for the work will go out early in the new year and the work, which includes reconstruction of the traffic islands, should be completed before the headquarters opens.

The board is paying the cost of the intersection work, he said.

The new headquarters was deemed necessary to house the all board’s administrative staff, which were spread out over five locations, and in order to avoid extensive renovation costs of its Education Centre at 100 Main St. West.

It is being built on the site of the former Crestwood school on Millwood Place, west of Upper Wentworth. The $31.6-million building was approved in 2011 after the school board sold Main St. West property to McMaster University for a health campus.

For over a year, administrative staff has been housed in space at the Standard Life Building, the Stelco Tower and the Robert Thompson Building, and using Hamilton City Hall for its board meetings.

The board is also moving the Mohawk Trail school to the new headquarters site. The school was built in 1882 and located at the corner of Mohawk Road West and West 15th Street.

That move will probably occur in March or April, said Cohen-White.
__________________
"Where architectural imagination is absent, the case is hopeless." - Louis Sullivan
Reply With Quote
     
     
  #122  
Old Posted Dec 11, 2013, 4:43 PM
HamiltonBoyInToronto HamiltonBoyInToronto is offline
Registered User
 
Join Date: Oct 2013
Location: Hamilton
Posts: 452
this is probably the worst decision that was ever made in Hamilton.... why would you move all of these city workers into the middle of a housing subdivision in the middle of suburban Hamilton mountain??!??!?!?!?!? this building would've been an incredible addition to the down town area on one of the many empty lots ...or in a retrofitted historic building ....
Reply With Quote
     
     
  #123  
Old Posted Dec 11, 2013, 4:56 PM
coalminecanary coalminecanary is offline
Registered User
 
Join Date: Jun 2007
Posts: 1,421
The most self-indulgent misuse of taxpayer dollars I have witnessed since I moved back to Hamilton in 97. This benefits nobody other than the overpaid exec and admin who want free parking close to the linc.

It's sickening
__________________
no clever signoff.
Reply With Quote
     
     
  #124  
Old Posted Dec 11, 2013, 5:15 PM
Pearlstreet's Avatar
Pearlstreet Pearlstreet is offline
Registered User
 
Join Date: Jan 2012
Location: Hamilton
Posts: 365
Quote:
Originally Posted by coalminecanary View Post
The most self-indulgent misuse of taxpayer dollars I have witnessed since I moved back to Hamilton in 97. This benefits nobody other than the overpaid exec and admin who want free parking close to the linc.

It's sickening
My gf and her fellow staff teach at a high school here in Hamilton and would agree with you.
__________________
Surfing the Hamilton renewal!
Reply With Quote
     
     
  #125  
Old Posted May 6, 2014, 3:47 AM
thomax's Avatar
thomax thomax is offline
Registered User
 
Join Date: May 2012
Location: Toronto
Posts: 5,380
Construction Update:


Source: My Photo

Larger Size:
Reply With Quote
     
     
  #126  
Old Posted Sep 11, 2014, 2:34 AM
SteelTown's Avatar
SteelTown SteelTown is offline
It's Hammer Time
 
Join Date: Mar 2004
Location: Hamilton
Posts: 19,872
Reply With Quote
     
     
  #127  
Old Posted Sep 11, 2014, 1:51 PM
mattgrande's Avatar
mattgrande mattgrande is offline
Registered User
 
Join Date: Jul 2010
Location: Hamilton
Posts: 1,240
$31.6m for the new building... how much did they get for the sale of the land?

I just can't help but think that money should've gone towards schools... I know they're getting some efficiencies out of this, and I don't really know how the funding works (ie, if that money could've gone towards schools, or if it was earmarked for Board of Ed buildings), but the whole thing seems gross.
__________________
Livin' At The Corner Of Dude And Catastrophe.
Reply With Quote
     
     
  #128  
Old Posted Mar 21, 2015, 2:15 PM
lucasmascotto's Avatar
lucasmascotto lucasmascotto is offline
Registered User
 
Join Date: Feb 2012
Location: Hamilton
Posts: 356
Final touches on Education Centre
(The Hamilton Spectator: Saturday, March 21st, 2015)

The Hamilton-Wentworth District School Board's new Education Centre by Lime Ridge Mall finally has the back-ordered glass safety panels needed to finish its main stairs and public gallery.

Board chair Todd White said he's been told the stairs will open by mid-April and be the last piece in finalizing the $31.6-million centre's construction.

Roped off, the stairs have been a noticeable eyesore since the board held its first meeting in November there because they are visible through the large glass windows that make up the front entrance.

Construction was initially slated to be completed by September, when staff moved into the three-level centre, but the buzzing whir of power saws was still loud enough at the March 4 policy committee meeting to make it hard to hear trustees at times.

"Aside from the stairs, it's 100 per cent aesthetic," White said of the remaining work, which includes fixing scratches and other minor damage.
Reply With Quote
     
     
  #129  
Old Posted Jun 17, 2015, 5:10 AM
thomax's Avatar
thomax thomax is offline
Registered User
 
Join Date: May 2012
Location: Toronto
Posts: 5,380
Reply With Quote
     
     
  #130  
Old Posted Jun 17, 2015, 5:21 AM
Katrillion's Avatar
Katrillion Katrillion is offline
Registered User
 
Join Date: Jun 2013
Location: Hamilton
Posts: 131
It's a real shame they chose such a suburban, difficult to get to, location and built a building that you wouldn't never find in a dense, urban city.
Reply With Quote
     
     
  #131  
Old Posted Jun 17, 2015, 6:05 AM
matt602's Avatar
matt602 matt602 is offline
Hammer'd
 
Join Date: Jan 2006
Location: Hamilton, ON
Posts: 4,751
I've seen big box stores with less of a walk to the front doors. Ridiculous. Really shows what the school board's priorities are.
__________________
"Above all, Hamilton must learn to think like a city, not a suburban hybrid where residents drive everywhere. What makes Hamilton interesting is the fact it's a city. The sprawl that surrounds it, which can be found all over North America, is running out of time."
Reply With Quote
     
     
  #132  
Old Posted Jun 17, 2015, 1:12 PM
king10 king10 is offline
Registered User
 
Join Date: Feb 2009
Location: Hamilton
Posts: 2,761
Looks like some tech office you'd find in suburban california. (not a good thing)
Reply With Quote
     
     
  #133  
Old Posted Jun 17, 2015, 3:24 PM
markbarbera markbarbera is offline
Registered User
 
Join Date: May 2007
Location: Hamilton
Posts: 3,050
Quote:
Originally Posted by matt602 View Post
I've seen big box stores with less of a walk to the front doors. Ridiculous. Really shows what the school board's priorities are.
The photograph makes the walkway look much longer than it actually is. It is about 25 metres in length. For perspective, the pedestrian walkway proposed to connect MacNab Terminal to Hunter GO Station is about 300 metres in length all told.
__________________
"A government that robs Peter to pay Paul can always depend on the support of Paul"
-George Bernard Shaw
Reply With Quote
     
     
  #134  
Old Posted Jun 17, 2015, 4:23 PM
ScreamingViking's Avatar
ScreamingViking ScreamingViking is offline
Ham-burgher
 
Join Date: Jun 2013
Location: Hamilton
Posts: 6,461
Putting aside the issue that the Board should have stayed downtown, I think the new building itself looks great.
Reply With Quote
     
     
  #135  
Old Posted Jun 17, 2015, 10:08 PM
davidcappi's Avatar
davidcappi davidcappi is offline
Registered User
 
Join Date: Oct 2013
Posts: 1,992
This would have been cool downtown surrounded by trees
Reply With Quote
     
     
  #136  
Old Posted Feb 24, 2016, 5:49 PM
thomax's Avatar
thomax thomax is offline
Registered User
 
Join Date: May 2012
Location: Toronto
Posts: 5,380
Reply With Quote
     
     
  #137  
Old Posted Feb 24, 2016, 8:13 PM
The Gore The Gore is offline
Registered User
 
Join Date: Aug 2014
Posts: 112
should have been downtown
Reply With Quote
     
     
  #138  
Old Posted Feb 24, 2016, 11:36 PM
Dr Awesomesauce's Avatar
Dr Awesomesauce Dr Awesomesauce is offline
Registered User
 
Join Date: Jan 2010
Location: BEYOND THE OUTER RIM
Posts: 5,889
Out of sight. Out of mind. Check and mate.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Hamilton > Downtown & City of Hamilton
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 10:48 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.