  #2081  
Old Posted Jun 4, 2015, 7:29 PM
Plokoon11 Plokoon11 is offline
Registered User
 
Join Date: Jun 2007
Posts: 1,698
Excellent thanks for the pictures! Thank goodness they didn't pick the donut deck, it would of be very strange.

And also, the crane is going up! I believe they will be putting 2 cranes up, one on the side and the core crane.
Reply With Quote
     
     
  #2082  
Old Posted Jun 4, 2015, 7:53 PM
summersm343's Avatar
summersm343 summersm343 is offline
Moderator
 
Join Date: Oct 2011
Location: Philadelphia
Posts: 18,362
Black tower crane going up on top of the steel on the west side.
Reply With Quote
     
     
  #2083  
Old Posted Jun 5, 2015, 12:15 AM
Zapatan's Avatar
Zapatan Zapatan is offline
DENNAB
 
Join Date: Aug 2009
Location: NA - Europe
Posts: 6,043
The donut looked terrible good lord!

This building is pretty awesome. I'm not sure where the rumors of a height increase came from but even in it's current form it'll change Philly quite a bit!
Reply With Quote
     
     
  #2084  
Old Posted Jun 5, 2015, 2:35 AM
tower's Avatar
tower tower is offline
resu deretsiger
 
Join Date: Nov 2003
Location: fishtown philadelphia
Posts: 896
the donut building could be cool as a shorter tower in a different location

but as a center piece it's just weird as shit
Reply With Quote
     
     
  #2085  
Old Posted Jun 5, 2015, 3:20 AM
summersm343's Avatar
summersm343 summersm343 is offline
Moderator
 
Join Date: Oct 2011
Location: Philadelphia
Posts: 18,362
Update from Building Philly

First crane going up!!



https://www.facebook.com/BuildingPhilly
Reply With Quote
     
     
  #2086  
Old Posted Jun 5, 2015, 1:05 PM
Philly Fan Philly Fan is offline
Registered User
 
Join Date: Feb 2013
Posts: 2,479
Just drove by--LOTS of guys apparently working on erecting both cranes.
Reply With Quote
     
     
  #2087  
Old Posted Jun 6, 2015, 12:11 AM
philatonian's Avatar
philatonian philatonian is offline
Registered User
 
Join Date: May 2008
Location: Philadelphia
Posts: 596
Quote:
Originally Posted by tower View Post
the donut building could be cool as a shorter tower in a different location

but as a center piece it's just weird as shit
It reminds me a little too much of Knoxville's Sunsphere.
__________________
Philly Bricks
Reply With Quote
     
     
  #2088  
Old Posted Jun 6, 2015, 1:00 PM
Joey DeVeetz Joey DeVeetz is offline
Registered User
 
Join Date: Jan 2015
Posts: 13
So now that we know the crane will be erected on top of the steel structure, what was that square base they were working on at the floor on the west side. Was the original intent to place the crane there and then plans changed?
Reply With Quote
     
     
  #2089  
Old Posted Jun 6, 2015, 1:48 PM
Philly Fan Philly Fan is offline
Registered User
 
Join Date: Feb 2013
Posts: 2,479
Quote:
Originally Posted by Joey DeVeetz View Post
So now that we know the crane will be erected on top of the steel structure, what was that square base they were working on at the floor on the west side. Was the original intent to place the crane there and then plans changed?
Pretty sure there are going to be (at least) two tower cranes. I think someone mentioned that further up this thread, and when I drove by yesterday (down 19th Street), it looked to me as if there were two separate tower cranes being erected (one on or adjacent to the core, and another nearby on the ground). Which would make sense for a project of this size, and given the need to be constructing the core while the attached steel structure is also being erected, and taking into account that this core will be near one side of the tower and not near the center.

Granted that I was driving during morning rush hour, and couldn't slow down or stop to take a good, long look. But that's what it looked like to me as a I drove by.
Reply With Quote
     
     
  #2090  
Old Posted Jun 6, 2015, 1:51 PM
RET48 RET48 is offline
Registered User
 
Join Date: May 2007
Posts: 10
(At least) two cranes were in the plan all along. On a project like this, changes "on the fly" are seldom made. My guess is that the black (Cornell) crane is on top of the steel because it couldn't be located on the bathtub floor without interfering with erection of the steel. I may be wrong, but I suspect that it will be used to lift steel on the west side of the core and to lift concrete mix to the core itself. The red crane can be on the floor because it won't interfere with construction there. Remember that the design includes large, three-floor (?) atria on the east side of the core. My guess is that the red crane will be situated within the atria but close to their western edges.

Please note that I'm not an engineer or project manager. The above is just my theory!
Reply With Quote
     
     
  #2091  
Old Posted Jun 7, 2015, 5:04 AM
87 Astro-t 87 Astro-t is offline
Registered User
 
Join Date: Jun 2015
Posts: 1
The red frame on the floor looks like the base to a hoist or construction elevator.
Reply With Quote
     
     
  #2092  
Old Posted Jun 8, 2015, 8:20 PM
BenKatzPhillytoParis BenKatzPhillytoParis is offline
Registered User
 
Join Date: Oct 2013
Posts: 313
So is someone going to post a pic of the CITC cranes? I would if I were in Philly ;-)
Reply With Quote
     
     
  #2093  
Old Posted Jun 8, 2015, 8:22 PM
phillyheights phillyheights is offline
Registered User
 
Join Date: Jun 2015
Posts: 39
that's what I was thinking, the Comcast CAM doesn't do much justice
Reply With Quote
     
     
  #2094  
Old Posted Jun 8, 2015, 8:28 PM
Plokoon11 Plokoon11 is offline
Registered User
 
Join Date: Jun 2007
Posts: 1,698
The cab of the one crane is on the ground.
Reply With Quote
     
     
  #2095  
Old Posted Jun 8, 2015, 10:23 PM
gw04 gw04 is offline
Registered User
 
Join Date: Jun 2015
Posts: 172




Reply With Quote
     
     
  #2096  
Old Posted Jun 8, 2015, 11:41 PM
summersm343's Avatar
summersm343 summersm343 is offline
Moderator
 
Join Date: Oct 2011
Location: Philadelphia
Posts: 18,362
Nice update Gw04! Thanks!
Reply With Quote
     
     
  #2097  
Old Posted Jun 9, 2015, 11:09 AM
thisisforreal's Avatar
thisisforreal thisisforreal is offline
Registered User
 
Join Date: Jun 2014
Posts: 751
I was there yesterday as well, tried to take a few photos from angles not previously shown (at least not in a while) and show its height relative to the Comcast building:





Reply With Quote
     
     
  #2098  
Old Posted Jun 9, 2015, 1:09 PM
Philly Fan Philly Fan is offline
Registered User
 
Join Date: Feb 2013
Posts: 2,479
Now that I see the photos of the tower crane being assembled out of both black and red components, I'm wondering if maybe what I saw when I drove by last Friday morning was actually just crews working on different parts of this single crane.

As always, time will tell.
Reply With Quote
     
     
  #2099  
Old Posted Jun 9, 2015, 7:03 PM
gw04 gw04 is offline
Registered User
 
Join Date: Jun 2015
Posts: 172
Reply With Quote
     
     
  #2100  
Old Posted Jun 9, 2015, 7:06 PM
joemustardo joemustardo is offline
Registered User
 
Join Date: Jul 2014
Posts: 81
I'm sorry but how long does it take to construct a crane? Like my god it's been a week. FMC had both of their cranes up within 2 days. I'm baffled by this.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Discussion Forums > Buildings & Architecture
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 7:39 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.